必发365

Service Hotline:0335-7168696
News
News
News

How much the formwork support height exceeds requires expert demonstration

Time:2022-07-04 13:09:57View count:



Some people don't know whether the supporting height of the meter board is more than 5 meters or 8 meters, which needs expert argumentation? Let's answer and analyze this problem.


If the formwork support height is more than 8 meters, it needs special scheme and expert demonstration. The erection height is 8m and above; Or the erection span is 18m or more, or the total construction load is 15kn / m ? And above; Or concentrated line load 20KN / M and above. Concrete formwork support works in divisional and subdivisional works with greater risk exceeding a certain scale: the erection height is 8m and above. In short, those over 8 meters need special plans and expert argumentation.


The Ministry of housing and urban rural development's JZ [2018] No. 31 document "Regulations on safety management of dangerous divisional and subdivisional works" stipulates:


1. Concrete formwork support works in divisional and subdivisional works with high risk: the erection height is 5M and above; Or erect a span of 10m or more; Or total construction load 10kn/m ? And above; Or concentrated line load 15kn/m and above; Or concrete formwork supporting works with a height greater than the horizontal projection width of the support and relatively independent and unconnected members.


2. Concrete formwork support works in divisional and subdivisional works with greater risk exceeding a certain scale: the erection height is 8m or more; Or the erection span is 18m or more, or the total construction load is 15kn/m ? And above; Or concentrated line load 20kn/m and above.


Note: some works of high formwork with a height of more than 8 meters need expert demonstration.


Preventive and monitoring measures for high support formwork:


1. For each high formwork project, materials that meet the standards should be selected, and professional technicians should design and calculate the foundation and support system, formulate a reasonable construction scheme, and set up in strict accordance with the scheme in the specific implementation process.


2. During the construction of high formwork, the construction scheme shall be carefully implemented to ensure the stability and reliability of the support system. After the formwork erection is completed, the inspection and acceptance shall be carried out to confirm that the formwork erection is completely made according to the construction scheme.


3. The support frame of high formwork generally adopts steel pipe frame system, which is erected by scaffolders. Formwork workers should also work according to the correct construction requirements during installation.


4. During the construction of high formwork, a stable operation platform shall be set, and channels shall be set between each floor, and protective measures such as emergency channels and guardrails shall be reserved.


For each high formwork project, materials that meet the standards should be selected, and professional technicians should design and calculate the foundation and support system, formulate a reasonable construction scheme, and set up in strict accordance with the scheme in the specific implementation process.



必发365官网(中国)乐趣网投天天必发
必发365官网(中国)乐趣网投天天必发
必发365官网(中国)乐趣网投天天必发
必发365官网(中国)乐趣网投天天必发
网站地图网站地图
友情链接:pg电子  leyu  尊龙凯时  旋乐吧  云顶集团  亚美AM8AG  bifa必发  尊龙凯时  南宫娱乐  尊龙凯时  尊龙凯时  凯时娱乐